How to calculate rate analysis of M10 grade concrete

Spread the love

What is M10 grade concrete ?

Contents

    • 0.1 What is M10 grade concrete ?
    • 0.2  what is M10 grade 1:3:6  concrete?
  • 1 How to calculate rate analysis of M10 grade concrete?

Concrete is described as per IS 456-2000 has designated the concrete mixes into two 1. Nominal Mix 2. Design Mix

In Nominal mix ratio of different material are already defined while in the design mix ratio is defined  after the testing with different trial mixes. Grade of concrete are such as as M10, M15, M20, M25, M30, M35 and M40 e.t.c.

In this designation the letter M refers to the mix and the number to the specified 28 day cube strength of mix in N/mm2. M10 concrete are used for leveling course, and bedding for footings.

How to calculate rate analysis of M10 grade concrete, M10 grade concrete,M10 grade concrete pcc,M10 grade concrete ratio,M10 grade concrete rate analysis

 what is M10 grade 1:3:6  concrete?

M10 is a lean concrete, M10 concrete is the strength offered by the concrete cube of 150mm dimension after 28 days,where strength is 10 N/mm2. M10 grade concrete have ratio of 1:3:6 in which it have 1 part of cement:3 part of sand: 6 parts of aggregate.

What is plain cement concrete|Specifications for Plain Cement Concrete

How to calculate rate analysis of M10 grade concrete?

Item Code Description
2.4  -Do- as per item No.2.03 but for providing and laying plain cement concrete (PCC) 1:3:6 with 1 part of cement: 3 parts of coarse sand: 6 parts of stone aggregate of size 37 mm and downgraded complete as directed.
CODE AS PER DSR 2014 Description Unit Quantity Rate Amount
Details of cost for 1 cum. MATERIAL
293 Stone aggregate below 40 mm nominal size Cum 0.947 2116.8 2004.61
2206 Carriage of Stone aggregate below 40 mm nominal size Cum 0.947 112.79 106.81
Stone Dust cum 0.47 3245 1525.15
2203 Carriage of Stone Dust cum 0.47 103.77 48.77
367 P.P.C Cement tonne 0.22 5700 1254.00
2209 Carriage of Cement tonne 0.22 92.24 20.29
155 Mason (average) day 0.1 500 50.00
114 Beldar day 1.63 368 599.84
101 Bhisti day 0.7 407 284.90
2 Hire Charges for Concrete Mixer day 0.07 800 56.00
12 Vibrator(Needle type 40mm) day 0.07 350 24.50
9999 Sundries L.S. 13.52 1.73 23.39
Total 5998.27
Add 15 % Contractor’s profit and overheads 899.74
cost for 1 cum. MATERIAL 6898.01

Note:-

  1. G.S.T Will be charge Extra as per actual on the work Contract
  2. Rate of the material will be based on the particular region

If you want to know the latest news About Civil Engineering and Want to get updated with the latest technology about Civil Engineering Like Our Page – Thetechface 

If you want to get the estimate of any particular project and need the complete Analysis of project then Feel Free to contact us.

 

Article by Vivek Mishra / Civil Engineering / M10 grade concrete, M10 grade concrete pcc, M10 grade concrete rate analysis, M10 grade concrete ratio Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Trending Now

  • Quality control tests in building construction
  • Price variation in Civil works contracts
  • How to fix MS Rolling Shutter|Fabrication of MS Rolling Shutter
  • COVID-19 18-44 age group vaccination CENTER IN Lucknow
  • Pre-Construction Chlorpyrifos AntiTermite Treatment
  • How to Calculate Brick work Quantity in a Circular Manhole
  • SRH Mystery Girl Kavya Maran’s Images
  • Fakhar Zaman 193 runs from 155 balls Run Out by Quinton De Kock
  • Interlocking Paver Block: How to lay Interlocking Concrete Paver Block?
  • Concrete road construction Steps
IndiBlogger - The Indian Blogger Community

Copyright © 2022 · Education Pro Theme on Genesis Framework · WordPress · Log in