Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6

December 25, 2017 by Vivek Mishra Leave a Comment

Spread the love

Brick masonry in superstructure in Cement Mortar (CM) 1:6

In many Tender documents you have got a item with this Description “Providing and constructing brick masonry in any shape in Cement Mortar (CM) 1:6 (1 part cement and 6 part coarse sand) in all works with approved quality bricks In foundation at all levels below and up to highest plinth level”

TMT Steel Bar price per kg Calculator

Many Engineer Feels lots of problem while Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6 . We have came up with the simple method so that you don’t have to wait for anyone or dependent on anybody while Estimating Brick masonry in superstructure in Cement Mortar (CM) 1:6 .

Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6

Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6-

Item Code Description
-Do- as per item No.3.01 but for providing and constructing Brick masonry in superstructure at all heights above highest plinth level.
CODE AS PER DSR 2014 Description Unit Quantity Rate Amount
Cost of 1 cubic Meter
2602 Common burnt clay F.P.S bricks class designation 150kg/sqm 1000 Nos 0.494 6000 2964.00
Cement mortar 1 : 6
3.11 Rate as per Item Number 3.11 of SH: Mortars Cum 0.25 6091.13 1522.78
2201 Carrige of Bricks 1000 Nos 0.494 276.72 136.70
9999 Sundries L.S 2.73 1.73 4.72
LABOUR 0.00
123 Mason (brick layer) 1st class day 0.47 500 235.00
124 Mason (brick layer) 2nd class day 0.47 450 211.50
115 Coolie day 1.8 368 662.40
101 Bhisti day 0.2 407 81.40
9999 Scaffolding L.S 22.36 1.73 38.68
Total 5857.19
Add 15 % Contractor’s profit and overheads 878.58
Rate per Cubic Meter of Brick work 6735.77

जब आप अपनी परियोजना की योजना बना रहे हैं तो यह आपके लिए बहुत महत्वपूर्ण होगा कि आप अपनी दीवार में ईंटों की संख्या की गणना कैसे कर सकें

निर्माण में उपयोग करने वाली सभी ईंट पानी में अच्छी तरह से भिगोए जाते हैं ताकि वे मोर्टार से पानी को अवशोषित न करें।

If you need a estimation of Bill of Quantities for your Tender work, Feel free to contact through the Form we will provide you the complete Estimation of the Project.

Filed Under: Civil Engineering Tagged With: Brick in superstructure, Brick masonry in superstructure, Brick masonry superstructure, Brickwork in Masonry Building

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Trending Now

  • Cement Concrete Road Construction Method | Procedure of RCC road construction
  • How to overcome Office stress | Office stress relief Methods
  • Different Types of Foundation Used in Construction
  • How to resolve CIBIL report disputes | Process to Remove Wrong Entry in CIBIL Report
  • Sieve analysis Test of coarse aggregate
  • Government job opportunities available in India after completing an MBA degree
  • What is WMM in Road Construction?
  • Effects of too much water in concrete
  • What is the scope of M.B.A. after civil engineering?
  • Calculate concrete of a circular column in cubic meter
IndiBlogger - The Indian Blogger Community

Copyright © 2023 · Magazine Pro Theme on Genesis Framework · WordPress · Log in