INJECTION GROUTING Rate Analysis|INJECTION GROUTING Per Square Meter Rate
Waterproofing treatment of RCC water tanks/ lift pits INJECTION GROUTING is done by the Providing & Fixing uPVC Nozzels, from Inside after shutter opening Only on construction joints/ honey comb/ cracks at leak area’s Due to Water test, needed pressure grouting of cement slurry admixed with Fosroc Chemical Conplast WL @ 300 ml/ Bag of cement , by providing 12mm dia PVC/ Plastic Nozzles, Final Cement slurry Grouting (after 28 Days), Using 140 PSI hand operated Grouting Pump, Finally Cutting & Sealing of Nozzle. Injection Grouting at weak areas/ Honey comb/ Const. In the case of Contract work we will have to provide a Guarantee of 10 Years for Leakage Proof of WTP Tank.
TMT Steel Bar price per kg Calculator
Waterproofing treatment of RCC water tanks/ lift pits INJECTION GROUTING
While If we properly follow the Waterproofing treatment of RCC water tanks/ lift pits INJECTION GROUTING methods then after one time it is done you will feel safe from leakage till any effect take place in the tank or pit due to structural or any other failure.
Injection grouting is usually carried out from the surface of RCC water tanks/ lift pits etc. This process is done by the filling of cracks, filling of open joints, and filling of voids with a Chemichal. Materials used in this process are cement grout, polymer-cement slurry, epoxy, urethane, and high-molecular-weight methacrylate .
Injection Grouting Service|Injection Grouting Contractor| Injection Grouting Service Uttar Pradesh
If you are in search of Injection Grouting Contractor in Uttar Pradesh,Waterproofing treatment of RCC water tanks/ lift pits INJECTION GROUTING Services with a Guarantee of Ten years then Contact Us.
INJECTION GROUTING Rate Analysis|INJECTION GROUTING Per Square Meter Rate
S.no | Description | Unit | Quantity | Rate | Amount |
INJECTION GROUTING : Providing & Fixing uPVC Nozzels, from Inside after shutter opening : Only on construction joints/ honey comb/ cracks at leak area’s Due to Water test, needed pressure grouting of cement slurry admixed with Fosroc Chemical Conplast WL @ 300 ml/ Bag of cement , by providing 12mm dia PVC/ Plastic Nozzles, Final Cement slurry Grouting (after 28 Days), Using 140 PSI hand operated Grouting Pump, Finally Cutting & Sealing of Nozzle. Injection Grouting at weak areas/ Honey comb/ Const. Providing a Gurantee of 10 Years for Leakage Proof of WTP Tank . Rates are Exclusive of GST. | |||||
Details of cost for 1 Sqm MATERIAL (For Vertical Wall) | |||||
1 | 12mm dia PVC/ Plastic Nozzles 5 Per Sqm @Rs. 40.00 Per No | Sqm | 5 | 25 | 125.00 |
2 | Chemichal Fosroc Conplast WL @ 300 ml/ Bag of cement | Sqm | 300 | 0.14 | 42.00 |
3 | Cement Slurry 5 Kg Per Sqm | sqm | 5 | 6 | 30.00 |
4 | Hire Charges for Grouting Pump | sqm | 1 | 75 | 75.00 |
5 | Mason | day | 0.1 | 450 | 45.00 |
6 | Beldar | day | 1 | 325 | 325.00 |
Total Amount | 642.00 | ||||
Contractor Profit @10% | 64.20 | ||||
Rate per Sqm Rs. | 706.20 |