Brick masonry in superstructure in Cement Mortar (CM) 1:6
In many Tender documents you have got a item with this Description “Providing and constructing brick masonry in any shape in Cement Mortar (CM) 1:6 (1 part cement and 6 part coarse sand) in all works with approved quality bricks In foundation at all levels below and up to highest plinth level”
TMT Steel Bar price per kg Calculator
Many Engineer Feels lots of problem while Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6 . We have came up with the simple method so that you don’t have to wait for anyone or dependent on anybody while Estimating Brick masonry in superstructure in Cement Mortar (CM) 1:6 .
Estimation of Brick masonry in superstructure in Cement Mortar (CM) 1:6-
Item Code | Description | ||||
-Do- as per item No.3.01 but for providing and constructing Brick masonry in superstructure at all heights above highest plinth level. | |||||
CODE AS PER DSR 2014 | Description | Unit | Quantity | Rate | Amount |
Cost of 1 cubic Meter | |||||
2602 | Common burnt clay F.P.S bricks class designation 150kg/sqm | 1000 Nos | 0.494 | 6000 | 2964.00 |
Cement mortar 1 : 6 | |||||
3.11 | Rate as per Item Number 3.11 of SH: Mortars | Cum | 0.25 | 6091.13 | 1522.78 |
2201 | Carrige of Bricks | 1000 Nos | 0.494 | 276.72 | 136.70 |
9999 | Sundries | L.S | 2.73 | 1.73 | 4.72 |
LABOUR | 0.00 | ||||
123 | Mason (brick layer) 1st class | day | 0.47 | 500 | 235.00 |
124 | Mason (brick layer) 2nd class | day | 0.47 | 450 | 211.50 |
115 | Coolie | day | 1.8 | 368 | 662.40 |
101 | Bhisti | day | 0.2 | 407 | 81.40 |
9999 | Scaffolding | L.S | 22.36 | 1.73 | 38.68 |
Total | 5857.19 | ||||
Add 15 % Contractor’s profit and overheads | 878.58 | ||||
Rate per Cubic Meter of Brick work | 6735.77 |
जब आप अपनी परियोजना की योजना बना रहे हैं तो यह आपके लिए बहुत महत्वपूर्ण होगा कि आप अपनी दीवार में ईंटों की संख्या की गणना कैसे कर सकें
निर्माण में उपयोग करने वाली सभी ईंट पानी में अच्छी तरह से भिगोए जाते हैं ताकि वे मोर्टार से पानी को अवशोषित न करें।